AURORA PROJECT

Overview

The Aurora Project
Click image to enlarge

Regional

Location and Access
Click image to enlarge
Click image to enlarge

Regional

Geology

Aurora

Historical Work

*  Rare Earth Elements, Niobium & Phosphorus

Click image to enlarge

Future / Development Timeline

Q1-2026

Option Agreement

COMPLETE

  • Sign agreement to earn up to 80% ownership in the Aurora project

Q2-2026

Field Program

PLANNED

  • Perform property-wide airborne radiometric survey

Q3-2026

Drill Target Modelling

PLANNED

  • Compile and analyze all the historic and recently collected data

Q4-2026

Financial Raise

PLANNED

  • Use the drill targeting model to rank the best areas on the project for testing

Q1 2025

Drill Program

PLANNED

  • Test the structure for mineralogy, grade, and metallurgical potential

Future / Development Timeline

2022

Field Program

COMPLETE

  • Staked claim

  • Improved hand sample grades

  • Performed QEMSCAN analysis to examine host mineralogy

Q3 2023

Field Program

COMPLETE

  • Perform aeromagnetic survey to further reveal structure.

Q4 2023

Program Planning

ONGOING

  • Prepare exploration budgets.

  • Perform till sampling to test nearby anomaly.

2024

Financial Raise

 PENDING

  • Use magnetic survey results for drill targeting.

  • Drill test if warranted.

Q1 2025

Drill Program

 PENDING

  • Test the structure for mineralogy, grade, and metallurgical potential